Babington Hospital Boiler Plant Installation, Belper
EP Consulting has successfully completed a £170k boiler plant installation at Babington Hospital in Belper. This project, undertaken for Derbyshire Community Health Services NHS Trust, was designed to enhance the efficiency of the hospital's laundry facilities. Our work focused on delivering a reliable and energy-efficient solution that adheres to the latest industry standards.
Scope of Work
Our team managed the comprehensive installation of a new boiler plant tailored to the specific requirements of the hospital’s laundry operations. The project encompassed detailed feasibility studies, budget costing, and mechanical design. We ensured full compliance with Part L2 Building Regulations, demonstrating our commitment to high-quality, energy-efficient solutions for healthcare facilities.
Challenges and Solutions
A primary challenge was executing the installation with minimal disruption to the hospital’s laundry services. Our team coordinated closely with hospital staff to schedule work efficiently, maintaining operational continuity throughout the project. The selected boiler plant was designed for optimal performance, significantly enhancing the facility's operational efficiency and reliability.
Results and Impact
Completed within a 12-week timeframe, the new boiler plant that supports the hospital's laundry services with increased energy efficiency and reduced operational costs. The new system enhances the hospital’s capability to manage laundry demands effectively, reflecting EP Consulting's expertise in mechanical design and sustainable energy solutions.
Key Facts
Client
Derbyshire Community Health Services NHS Foundation Trust
Sector
Hospitals
Value
£170k
Location
Belper
Services
- Budget Costing
- Feasibility
- Mechanical Design
- Part L2 Building Regulations