Building Services Engineers

Hermitage Leisure Centre

Location: Leicestershire

Click Here To Enlarge

The remodelling of existing changing rooms to create a ‘village’ changing facility, including shower area and unisex toilets, and installation of a combined heat and power unit, environmental control plant and replacement of pool plant. The mechanical and electrical works were valued at £300k.


Architect: Turnkey Design Partnership

Project Manager: Turnkey Design Partnership

Contract Duration: 30 weeks

Contract Value: £1.2m


Roles

Feasibility

Budget Costing

Mechanical Design

Electrical Design

Part L2 Building Regulations